For the project to succeed, get off to a good start
For the project to
succeed, get off to a good start.
“Well begun is half done” - Aristotle
Any organisation won't start a project right away after the
Sponsor gives it the thumbs-up. The Project Sponsor and all the key
stakeholders come together to define the Project's goals in a clear statement
as part of a formal process called initiating. For those who are unfamiliar
with project management, the term sponsor simply refers to the body that
authorises the project's financial expenditures. All those who have an impact
on the project or who are impacted by it are considered stakeholders.
In the Initiating process, the business need as well as the benefits
due to the proposed solutions are evaluated by the Project Sponsor alongwith
the stakeholders and if necessary a Feasibility study is undertaken by a team which
is appointed by the Sponsor. Invariably, Benefit-cost analysis is worked out
and if the benefits outweigh the costs, the project is then taken into
consideration. The output of this Initiation process is a Project Charter which
is approved by the Sponsor. The Project Charter contains the information about
the Business need, Objectives, Solutions, Assumptions, Constraints, approximate
cost and time required etc. on a bird’s eye view. The estimations of the
initiation process shall not be construed as detailed ones. Rather they give a
rough idea about the time and money required to complete the project. They can
vary even by 50 - 100 % when compared with the detailed estimates which will be
worked out in the Planning stage later.
The Project Manager is also named in the Charter, though it
is always preferable to do so before the actual initiating process so that he
can participate in it and apply his skills. He takes the necessary precautions
to ensure that the proposed project is consistent with the Organization's
Strategic Plan, which means the Project aids in some way in the accomplishment
of the Organization's long-term goals. It must not hurt it even if it doesn't
support it. If not, the Sponsor will designate the project proposal for
rejection. The Project Charter’s approval authorizes the expenditure of funds for
carrying out the detailed planning.
The Planning Process should be undertaken to manage the
Scope, Time, Cost, Quality, Risk, Resources, Communications and Procurement.
The output of each of these processes will be the respective Management plans.
All these plans are to be integrated by the Project Manager into a Project
Management Plan which is the document that contains all the information
required about the Project. The estimations in this document are accurate
within +- 10%. So, The Cost and time required for the completion of the Project
can be narrowed down to +- 10 % by the Planning process. This is the greatest
advantage here. The sponsor can now reconsider whether to approve the project
management plan for the project's implementation OR to abandon the project. The
Risk Management Plan will also provide a clear understanding of the likely
risks that the Project will face and whether those risks may have any impact on
its completion. Thus the Sponsor can get a detailed document (Project
Management Plan) by spending a small amount, say 5-10% of the Project cost, for
the Planning process.
Approval of the Project Management Plan by the Sponsor
authorizes the execution of the Project.
Whether a project is large or small, the initiating and
planning stages must always be followed to assure success. Some planning
procedures might not be necessary for minor projects because they won't likely
have an impact. However, it is preferable to write a single sentence stating
that they are irrelevant and should not be taken into account. Therefore, any
new project manager who reads the plan will be assured that all industrial best
practices were rigorously observed during the planning stage.
So it is clear that the Project
Charter is important for the next Planning phase and the Project Management Plan is important
for the next Execution phase. Organisations may have different names for the
above two documents but the content remain the same.
Projects which undergo the above two processes are more likely
to end successful whereas those which skip the above processes are destined to
become failures. My own experience has shown me that some projects that didn't
go through the aforementioned two phases have failed miserably. I came to know
about a project which was mooted by a Sponsor without analysing the business
need & the proposed solutions. The project was meant to curb the theft of
fuel in the DG sets in telecommunication towers by providing energy meters. The
Sponsor believed that the energy usage reported in the meter would indicate
whether or not the DG had been used. However,
In order to determine whether the suggested solution will genuinely address and
meet the need, the initiating procedure was not carried out adequately. The
planning phase began and was approved. The project was completed at a
significant expense, and meters were installed in each tower. This does not,
however, resolve the issue because the consumer still needs to use the meter
readings to perform intricate calculations to determine whether the fuel was
taken. Therefore, the consumer made no use of the meter. While the project's
planned goals were achieved, the business problem was not resolved. The issue
persisted even after investing millions of rupees. This is a common instance of
a project failing owing to an inadequate Initiating.
Initiating process narrows down the solutions to the business
problems. It evaluates the effectiveness of the solutions one by one and goes
for the one that is most effective.
Planning process describes how efficiently the solutions can
be achieved in the earliest time at the least cost, with fewer resources etc.
So, Initiating is about Effectiveness whereas Planning is
about Efficiency. Compromising on efficiency can be tolerated to a certain
extent but not on the effectiveness.
To give one instance, You have made good preparations to
attend a friend's wedding. Everything went smoothly, including buying new
clothes for family members, purchasing an expensive gift to remember the
occasion, taking time off work, gathering with family, starting well on time,
getting to the destination on time for the least amount of money, etc.
Everything is completed quickly. However, you are unhappy to learn that you
brought the wrong package when it comes time to offer the gift.
A work well begun is half done
👌👌👌 very nice. Excellent
ReplyDeleteThank you for the first comment.
DeleteWhat happens if the Project do not achieve the Business needs? Who is held responsible?
ReplyDeleteIt's a very embarassing situation. The Project manager or his team cannot be held responsible because they have delivered what they have been told to. It becomes a failed concept. The Sponsor becomes answerable.
DeleteThe standard processes which are being followed in the industry before approving mega projects may be posted.
ReplyDeleteSure. Please follow this site.
DeleteSuper
ReplyDeleteWell explained
I'm pleased that it was helpful.
DeleteSuper sir
ReplyDeletePut more blog like this
Very useful
I'm pleased that it was helpful.
Delete